Warwick School
Refurbishment
Harrabin Construction was appointed Principal Contractor with contractor design portion including mechanical & electrical. The works comprised of working in multiple areas of the school & buildings within the overall site. There was a complete electrical installation throughout and extensive mechanical works including ventilation, heating, compressed air, cooling via air source heat pumps, hot & cold supplies and waste to new toilet facilities.
Erection of high-specification Gyproc metal stud partitions to divide the space with enhanced acoustic performance to minimise noise bleed between the 2 areas.
There were extensive fire-stopping works undertaken, this included pipe/cable penetrations, large ventilation ductwork, ceiling voids and fire breaks under partitions and within floor voids.
The project required phased handovers to facilitate the use of the office/teaching space ahead of the completion date. These areas included but were not limited to, the isolation of power, water and air conditioning works to facilitate the new connections/installations within a live environment, meaning careful coordination, communication and programming were paramount to the successful completion of these areas.
Changes to employers’ requirements were responded to positively and proactively resulting in programme requirements being achieved and excellent feedback from the Warwick School staff and contract administrator.
Key Accountabilities
- Work for an educational establishment within a live Primary School environment.
- Work in an occupied building by both staff and students.
- Ensure minimal disruption to the staff and students within the school during the construction phase.
Gallery:
Description
Value:£500,000
Client:Warwick School